GBRA Board of Directors hear from engineer, Lake Wood property owners

Posted

SEGUIN — The Guadalupe-Blanco River Authority Board of Directors meets once a month to discuss issues across the jurisdiction of the Authority. Once again Lake Wood was a discussion Item on the agenda. The board of directors, GBRA staff and several Lake Wood property owners spent an hour discussing the broken dam, offline hydroelectric facility and the future of unknown Lake Wood.

Board Chairman Rusty Brockman asked the board and staff to move Lake Wood discussion to the top of the agenda. He then made opening comments.

"Many of you are here today for agenda item number nine – having to do with the Lake Wood Dam. We are pleased you are attending today and we look forward to your comments. The staff and board are also appreciative of the opportunity we had last Thursday to present detailed information about the research and problem solving currently underway to resolve this difficult issue affecting the property owners on Lake Wood. That information provided a detailed look at the physical and financial implications facing the Guadalupe-Blanco River Authority as we work with you to come to a sound business solution that will satisfy everyone. As a board we stand by the work being performed by our GBRA team. During the last 12 months many changes have taken place among the leadership of GBRA; Those changes have brought strong leadership and highly-qualified and talented professionals all working to solve a problem. The problem has no quick and easy fix and we invite each of you to the table, to help with the solution. We all may not live on Lake Wood, but Lake Wood is certainly part of the GBRA family. We certainly have learned from this difficult issue that communication is extremely important. Our team might not have followed through by keeping property owners well informed of the process but the process has been consistent and ongoing to achieve answers and a solution. Our efforts going forward will require a team effort and we hope that all of you will come to the table and keep the discussion moving forward in a positive way. We thank you for your comments today and your commitment as we search for the best possible solution."

Brockman turned the meeting over to GBRA General Manager Kevin Patteson.

Patteson and GBRA Project Engineer Charlie Hickman then recapped the Thursday night presentation and public forum put on by GBRA at the JB Well Expo Center.

"What we're conducting now is our due diligence as to what the future of the hydrosystem is. The system was – as you are aware – was put into place in the 1930s, which means it was planned in the 1920s," Patteson said. “Hydro now is not going to look like it did then."

Patteson said while there has indeed been a dam gate failure at Lake Wood, GBRA needs to look forward at the needs of all the hydro facilities and all of the antiquated dam gates. GBRA operates six hydroelectric facilities with 15 dam gates between them.

"At Lake Wood, specifically the spillway gate replacement, there would be about $8.4 million," he said. "There is a significant contingency built in there, because we still have a lot of questions to answer moving toward resolution."

Patteson reported his exploration of financial avenues, which has already taken him to Washington, D.C. once and will have him there again on Monday. He said he is seeking local, state and federal funding, with the most promising avenue being the Water Development board, which offers a finance rate of less than one percent.

"Over 30 years there's a debt service in there of $300,000 a year," Patteson said. "That’s a challenge we are facing out at Lake Wood."

Patteson said his concern is how GBRA will fund that debt out of the hydrofacility. He said the purchaser has a contract and can cancel with just five years notice and GBRA needs to look forward and plan how a debt would be re-payed if there was no longer a purchaser.

Hickman showed the board the same presentation that was presented last Thursday night. The presentation covered the damage and failure at Lake Wood, causes, structural explanations and replacement alternatives.

According to Hickman the preferred replacement gate at Lake Wood would be the Obermeyer Gate, a simple steel plate raised and lowered by a giant rubber and Kevlar air bag.

With all this being reported, the floor was opened for Lake Wood property owners to speak out.

Dale Schellenberg and Joe Solansky have been heading up the informal Lake Wood property owners’ committee called Friends of Lakewood, for the last year. They each took the opportunity to speak to the board, along with several others, restating the conditions at the lake and reiterating concerns and questions for the board and staff.

The board and GBRA staff have assured the friends of Lakewood that they will continue to seek a solution.

In other business, the board honored Richard "Dicky" Maxwell for 41 years of dedicated work for GBRA and congratulated him on his retirement.

Lake Wood is also on the next GBRA Board of Directors Agenda. The meeting is scheduled for 10 a.m. Wednesday, April 19, at the GBRA Annex Building, located at 905 Nolan Street, in Seguin.